MRI departmental QA and auditing toolkit (TG-18/TG-270 display QA, ACR QC and audit checklists)

MRI departmental QA and auditing toolkit (TG-18/TG-270 display QA, ACR QC and audit checklists)

Display QA (AAPM TG-18 / TG-270), ACR scanner QC, coil & equipment checks, and audit schedules, with printable logs. Educational summary; follow your site’s QC manual and medical physicist’s programme.

Related
On this pageAudit CalendarDisplay QA (TG-18/270)Weekly Scanner QCAnnual Physicist TestsCoils & EquipmentAudits & GovernanceSources
Key points
  • Run a documented, scheduled, signed-off QC programme with named responsibility and action limits; log date, initials, values and pass/fail, plus the corrective action and re-test for any failure.
  • Where the ACR programme applies, run weekly phantom QC the same way each time and trend values against your site baseline: a value can be in tolerance yet still signal a failing component.
  • An on-screen TG18-QC pattern check is a quick visual check only; formal acceptance and annual display tests need the official patterns at native resolution and a calibrated photometer.
  • Put every clinical coil through QC at least annually and inspect its cables, housings and padding, because damaged cables are an RF burn risk, not just an image-quality problem.
  • Audit against a defined standard by sampling real records rather than asking staff; grade each finding, give it an owner and a date, and re-audit failures to close the loop.
Explain it simply
  • Quality checks follow a written, signed-off schedule with a named person in charge and set limits. Each check records the date, who did it, the results, and how any failure was fixed and rechecked.
  • In the ACR programme, staff scan a test object the same way each week and compare results with that scanner’s usual values. A result within limits can still show a part starting to fail.
  • Looking at a test picture on a reading screen is only a quick check. Proper screen testing uses the official test pictures at full resolution and a calibrated light meter.
  • Every coil placed on patients is tested at least yearly and checked for cracks and damage, because a damaged cable can burn the patient, not just spoil the pictures.
  • Audits check real records against a named standard instead of asking staff what they do. Each problem gets a grade, an owner and a deadline, and failures are checked again until fixed.

A guide only: follow your departmental protocols and regional requirements.

What a compliant MRI QA programme contains

Accreditation schemes (for example ACR and IAC in the US, the Diagnostic Imaging Accreditation Scheme in Australia, and the RCR–SCoR Quality Standard for Imaging in the UK) expect a documented, scheduled, signed-off QC programme with named responsibility, action limits, and evidence of corrective action. Use this matrix as your master schedule.

FrequencyTaskWhoRecord
DailyVisual walk-through: door/RF seal, alignment light, patient monitoring & alarm, emergency stop, table motion, room access signage, cryogen level indicatorMRI technologistDaily tick-sheet
Daily/WeeklyDisplay QC pattern check on acquisition console & reading workstations (visual)TechnologistDisplay QA log
WeeklyACR phantom QC: table position, centre frequency, transmitter gain, geometric accuracy, high-contrast resolution, low-contrast detectability, artifact reviewDesignated QC technologistWeekly QC log + trend chart
MonthlyVisual checklist (ACR): RF door contacts, coil cables/housings, phantom condition, monitors, emergency cart seal, cryogen trend reviewTechnologist / leadMonthly checklist
QuarterlyCoil rotation QC (each clinical coil through SNR/uniformity check over the year); safety self-audit spot checks; ferromagnetic detector functionLead technologistCoil log
AnnualMedical physicist/MR scientist performance evaluation; full display calibration (GSDF); MR safety programme audit (MRSO/MRMD); policy review; staff safety training renewalPhysicist + MRSO/MRMDAnnual report
Golden rule of trending: a QC value can be “in tolerance” and still signal a failing component. Plot weekly values (centre frequency drift, TG, SNR). A consistent slope matters more than any single point.
Back to contents

Display QA: AAPM TG-18 and TG-270

TG-18 (2005) defined the classic test patterns and criteria; AAPM Report 270 (2019) updates them for modern flat panels and defines four display categories: diagnostic, modality, clinical specialist and electronic health record (EHR) displays. The familiar TG18-QC pattern is still used for the quick visual check below.

Acceptance criteria (quick reference)

MetricDiagnostic (primary)Modality / secondaryNotes
Max luminance Lmax≥ 350 cd/m² (mammo ≥ 420)≥ 250 cd/m² (TG18 legacy: ≥100)ACR–AAPM–SIIM practice parameter values
Luminance ratio Lmax/L’min≥ 250≥ 100L’min includes ambient contribution
GSDF conformance (DICOM Part 14)within ±10%within ±20%Measured at 18 levels (TG18-LN) with photometer
Ambient ratio Lamb/Lmin< 1/4TG-270; achievable at 25–75 lux reading-room lighting
Luminance uniformity< 30% non-uniformity, where non-uniformity = 200 × (Lmax − Lmin)/(Lmax + Lmin), measured at the centre and four corners (TG-18)TG18-UNL pattern
Geometric distortion≤ 2%≤ 5%Rarely an issue on LCDs; check scaling artifacts

On-screen visual check (daily/weekly, no photometer)

Display the official AAPM TG18-QC test pattern full screen on the workstation, at normal reading-room lighting. All checks should pass on a calibrated display:

This is a quick visual check only. Formal acceptance and annual tests need the official TG18-QC / TG270-sQC patterns at native resolution plus a calibrated photometer. Browser scaling invalidates line-pair and luminance measurements. Download official patterns from AAPM Report 270.
Back to contents

Weekly scanner QC: the ACR technologist tests ACR large phantom

Run the same protocol every week (ACR T1 sagittal localizer + T1 axial series), same phantom position, after ≥ 30 min phantom temperature equilibration in the scan room. Record values and compare with your site baseline, not just the absolute limit.

TestHowExample action limit (set yours with your physicist)What failure suggests
1. Table position accuracyLand phantom, advance to isocentre, check indicator vs landmark± 5 mmTable drive/encoder wear
2. Centre frequencyRecord f₀ from prescanWeekly change within the limit your physicist sets (ACR worked example: 2 ppm a week, about 128 Hz at 1.5 T and 256 Hz at 3 T)Field drift: superconductor run-down, thermal or mechanical effects, shim-coil changes or nearby ferromagnetic material (ACR 2015); report a persistent trend to your physicist and service engineer
3. Transmitter gain / attenuationRecord TG (or reference voltage) from prescanChange within the limit your physicist sets (ACR records transmitter gain or attenuation in dB); needing more gain (less attenuation) for the same phantom suggests an RF chain problemRF chain (amplifier, body coil, tuning) degradation
4. Geometric accuracyMeasure phantom length on localizer, diameter on axial slice 5148 ± 2 mm (length); 190 ± 2 mm (diameter)Gradient calibration or shim error; critical for stereotaxy/RT planning
5. High-contrast spatial resolutionResolve hole arrays on slice 11.0 mm resolved (both directions)Gradient performance, eddy currents, ghosting
6. Low-contrast detectabilityCount complete spokes, slices 8–11≥ 37 total spokes at 3 T; below 3 T the minimum depends on field strength (see the current ACR Large and Medium Phantom Test Guidance); weekly = watch trend vs baselineLoss of SNR or contrast-to-noise anywhere in the chain, or new ghosting; watch the trend against baseline
7. Artifact evaluationWindowed review of all slicesNo new ghosting, zipper, shading, spikesRF leak (door seal!), spike noise = gradient/RF arcing
Documentation counts as much as the numbers: each entry needs date, operator initials, values, pass/fail, and, for any failure, the corrective action and re-test result. Blank boxes are audit findings.
Back to contents

Annual medical physicist / MR scientist evaluation

Performed at acceptance, annually, and after major repairs (gradient/RF amplifier, coil replacement, software upgrade, magnet ramp).

TestTypical criterion
Magnetic field homogeneityMeets vendor spec over defined DSV (e.g. bandwidth-difference or phase-map method); record ppm over 35 cm DSV
Slice position accuracy± 5 mm (ACR phantom crossed wedges, slices 1 & 11)
Slice thickness accuracy5.0 ± 0.7 mm (signal ramps, slice 1)
Radiofrequency coil checks: all clinical coilsSNR vs baseline (typically within ±10–15%); percent image uniformity (PIU) ≥ 87.5% below 3 T, ≥ 82% at 3 T (volume coils); percent signal ghosting ≤ 2.5%
Soft-copy display & workstation QCFull TG-270 photometer assessment + GSDF calibration
Geometric accuracy, HCSR, LCD, TG/f₀ reviewAs weekly tests, measured independently + review of technologist QC programme and trends
MR safety programme reviewZone signage/access, screening forms current, ferromagnetic detection, cryogen vent inspection, emergency procedures, training records (often with MRSO/MRMD)
The annual report should state: tests performed, results vs criteria, comparison with prior year, deficiencies with recommended actions, and a summary statement of scanner suitability for clinical use.
Back to contents

Coil & ancillary equipment QC

Coil rotation programme

Every clinical coil should pass through QC at least annually (ACR 2015: the physicist’s annual evaluation tests all RF coils used clinically). How the checks are spread through the year is a local choice agreed with your physicist. For each coil: appropriate phantom, standard sequence, record SNR, PIU, ghosting, and inspect cables, strain reliefs, housings and padding for cracks (RF burn risk from damaged cables is a safety issue, not just image quality).

Equipment checks

ItemFrequencyCheck
Cryogen level / cold-headDaily–weeklyHelium % logged and trended; cold-head “chirp” audible; alert vendor on abnormal consumption
Chiller / cryocooler waterDaily walk-byTemperatures & flow in range; alarms functional
RF door seal / penetration panelMonthly + on artifactFinger-stock contacts intact and clean; door closes fully; no unauthorised cable runs through waveguide
Patient monitoring & commsDailySqueeze-ball alarm, intercom, MR Conditional monitors/pumps function-checked and within service dates
Emergency equipmentDaily/weeklyMR Conditional or Zone-III-staged crash equipment; non-magnetic extinguisher present; evacuation route clear; quench button covers intact
Ferromagnetic detectorQuarterlyFunction test with test object; log
PhantomsOngoingNo bubbles/leaks/crystallisation; stored in scan room for temperature stability
Back to contents

Departmental audits & governance

The audit stack accreditation looks for

AuditCadenceContent
MR safety self-auditAnnual (spot-check quarterly)Zones/signage, screening compliance sampling, device/implant workflow, staff training currency, incident log review; see our self-audit checklist
QC programme auditAnnual (physicist)Completeness of logs, trend review, corrective-action closure
Protocol auditAnnualScanner protocols vs departmental SOPs; unauthorised edits; sequence-version drift across scanners; see departmental protocols & SOPs
Image-quality auditRollingReject/repeat analysis, radiologist feedback loop, artifact log review
Incident & near-miss reviewEach event + annual summaryProjectile events, burns, screening failures, contrast reactions; feed into training
Documentation reviewAnnualPolicies version-controlled, signed, review-dated; screening forms current edition

Running an audit that survives inspection

Define the standard being audited against (ACR, MHRA, RANZCR; see our guideline comparison), sample real records rather than asking staff what they do, grade findings (compliant / partial / non-compliant), assign each finding an owner and a date, and re-audit the failures. An audit without a closed corrective-action loop is a paperwork exercise.

Printable templates: matching Word log sheets (display QA log, weekly QC log, coil/equipment log, annual audit checklist) accompany this page. Download from the resources section.
Back to contents

Sources

Sources (6)

6 sources listed

  1. AAPM Report 270: Display Quality Assurance (2019)
  2. Samei et al., AAPM TG18 executive summary, Med Phys 2005
  3. ACR Large/Medium Phantom Testing: MRI (revised 6 Feb 2026)
  4. ACR MRI Quality Control Manual (2015)
  5. ACR–AAPM Technical Standard for Diagnostic MR Equipment Performance Monitoring
  6. ISMRM safety resources.

Educational content, not a substitute for your accreditation body’s current manuals.

More in Running the department

Next in Running the department: MRI for radiology nurses

Educational reference for imaging professionals. It does not replace local policy, manufacturer labelling or clinical judgement.